As I was watching the contractor put the insulation up in the ceiling I was reminded why I like doing bikes.
We had a City inspector out at noon but I wasn't able to find out what the story was.
I'll find out Monday.
Right now it looks like we have the drywall to do, bath fixtures, bicycle parking inside and out side, fire extinguishers, parking lot paint, tire bumpers, handicap hardware, some signs that read, "Do not stack anything above the red line by order of the fire Marshall." Finish electrical, Cable internet, set up the network, build the work benches, paint, and start moving parts in.
Should have it all done by tomorrow morning at 9